Separate person-minutes from elapsed time
Total participant effort and elapsed duration answer different questions.
When people work in parallel, their summed durations do not necessarily give elapsed time. Decide whether you need total effort or the elapsed interval. Label the result and its assumptions; dependencies or shared resources can change the calculation.
What to do
- Record each person's work interval and identify any shared resource, dependency or waiting time.
- For total effort, add the participants' working durations and label the unit “person-minutes.”
- For elapsed time, compare the common start with the last finish and check the parallel-work assumptions.
Example
Fictional example: Mia checks captions for 10 minutes while Leo checks independent links for 15. They start together and work without waiting. This gives 25 person-minutes and 15 elapsed minutes. One person doing both tasks sequentially would have a different elapsed duration.