Remove an overlap in one person’s plan
Check overlaps even when the total work duration fits.
Enough total minutes do not guarantee a feasible schedule. One person cannot give two tasks full attention simultaneously. If their starts are flexible, check a rearrangement inside the window before abandoning either result.
What to do
- Write each task’s start, finish and performer alongside its actual constraints.
- Find any interval assigned twice to the same person, beyond adding durations.
- Move a flexible block, then recheck the window boundaries and all overlaps.
Example
Fictional model: one person, 09:00–10:00, independent A and B requiring 30 minutes each, with no additional setup. A is 09:00–09:30; B is 09:20–09:50, overlapping for 10 minutes. Moving B to 09:30–10:00 fits both sequentially. The 60-minute workload is unchanged. These are model conditions, not a workplace standard.