Separate batch setup from time per item
Do not multiply a one-time setup by the item count.
If setup is needed once for the entire batch, count it separately from repeated work. Identify what actually repeats for each item, then add setup to quantity multiplied by time per item. This is a sequential-work model, not a guarantee of exact duration.
What to do
- Separate one-time stages from stages repeated for every item.
- Record the item count and an illustrative duration per item. Use one time unit throughout the calculation.
- Calculate the sum and add known breaks or extra operations separately when applicable.
Example
Fictional example: setup takes 15 minutes, followed by 3 items at 4 minutes each: 3×4=12, so 15+12=27. No setup repeats between items.