Review an overdue project task before changing its date

A past date tells you that the recorded plan needs attention. It does not tell you whether the work is finished, still useful or ready for a new date.

Start with one task without subtasks, called a leaf task here. Check its actual result before deciding whether to complete it, reschedule it or keep it in the project without a date.

Painted illustration: two students planning their study at a library table.

Understand why a task is overdue

In Project calendar, Overdue tasks lists available unfinished tasks whose planned date is earlier than today's local date. Archived branches are excluded. A task scheduled for today is not overdue merely because its work is still open.

Read the task's title and note in Projects. The red state is a prompt to review a plan, not a reason to report work that never happened.

Choose the decision from the actual work

First wait for saving to finish and resolve pending marks or board changes. Determine whether the leaf task is actually finished. If it is still needed, decide whether you can name a realistic new date; if not, an undated task may be the honest next state.

  1. Open Project calendar and identify one overdue task without subtasks.
  2. Resolve pending changes, read the project note and inspect the actual work outside the planner.
  3. Mark that leaf task complete only if its stated result is genuinely finished.
  4. Otherwise choose Reschedule and save a realistic date, or use the calendar row's × to clear only the date.
  5. Check the new calendar entry, the retained undated task or the genuine completed state, according to your decision.

Example: a draft layout that missed its date

“Check the draft layout” is unfinished and dated before today. Open the actual layout and read the note. If the promised checks are complete, mark that leaf task complete. If the checks still need a specific work session, choose Reschedule, enter the new date and save the date editor.

If you cannot choose a date yet, use × on that task's calendar row to clear only the date. The task and its note remain in the project. An undated unfinished task is not counted as a completed check, and moving its date does not do the check.

Keep parent groups and daily choices separate

Use a leaf task for this procedure. Marking a parent task complete affects its descendants and can close more work than you intended. Do not close a group to remove one red date.

The × beside a task in the open day removes only its daily selection; the × in the calendar clears its date. Rescheduling a calendar task does not automatically choose it for another day's plan or send an external reminder.

Verify the selected outcome

For a new date, check that the task appears on that calendar date with the correct note. After clearing the date, find the unfinished task in its project. After genuine completion, verify its completed state and the actual checked result.

The project-planning and next-action guides help you make a task specific. The installation guide explains setup. Access costs 30 USDT per calendar year for one computer, with a separate licence for a second computer.

Check the result before you finish

  • Find the task on its new date, without a date, or completed, according to the decision you actually made.
  • Check the task's real output and its separate daily selection. Rescheduling does not perform the work or select another day automatically.

Questions about this guide

Does an overdue task move itself to today?
No. You decide on a new date or remove the old one yourself.
Can I close the parent group to remove the warning?
That can also complete its descendants. Review the individual leaf task and record only work actually finished.
Does clearing the calendar date remove the task from its project?
No. The task remains available in the project without that date. Removing a daily selection is a separate operation.